RES 1298RESOLUTION NO.1298
A RESOLUTION revising and extending the Comprehensive
Street Program for an additional six (6)years.
WHEREAS,pursuant to the requirements of RCW 35.77.010,the City of Camas did ,by
Resolution No.1272 adopt a Comprehensive Street Program for the ensuing six (6)years,and
WHEREAS,said law requires the City revise and extend said Comprehensive Street
Program annually,and
WHEREAS,pursuant to said law,the City Council of the City of Camas being the
legislative body of said City did hold a public hearing on said revised Comprehensive Plan at
7:00 p.m .at the Camas Municipal Center in Camas,Washington,on the 2nd day of June 2014,
and
WHEREAS,there were no written or oral objections to the revised Comprehensive Plan
as prepared by the City of Camas relative to the street program for the ensuing six (6)years
within the City of Camas.
NOW,THEREFORE,BE IT RESOLVED by the Council of the City of Camas that the
Comprehensive Street Program heretofore adopted and revised by the City Engineer for the City
of Camas,as submitted to the City Council for the City of Camas,be and the same is hereby
adopted and extended for an additional six (6)year period from the date thereof.
BE IT FURTHER RESOLVED,that the City Clerk file a copy of said revised
Comprehensive Street Program for the ensuing six (6 )years,together with a copy of this
resolution ,with the Secretary of Transportation of the State of Washington .
Resolution No.1298
Page 2
PASSED by the Council and APPROVED by the Mayor this 16 th day of June 2014.
Q '/fyj .—>>SIGNED:
avor
ATTEST:
Clerk
APPRO as to form:
C\y A 'orney
SixYearTransportationImprovementProgramWashingtonStateDepartmentofTransportationAgency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM:2015TO:202«HearingDale:AmendDale:6/2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNoC.ProjectTitleI)RoadNameorNumberE.Bcgm&EndTerminiKProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnlyiseO•5,JDB.STIPIDFundSourceInformationExpenditureSchedule(LocalAgency)0St16$llT3c3S2£gzPhaseStart(yyyyj.:&*FederalFundCode5StaleFundCodeEnvir.TyperowRequiredasFederalFundsStateFundsI.ocalFundsTotalFundsc—H1st2nd3rd4ththru6thJa5§B£GStructureIDmr..3256781049II12131415161718192021CN3/1/2015PWTF150025017501750NW6thAvcuneNWNorwoodSt.toNEAdamsfrom:Norwoodtrafficsignal,re-surfacing,pedestrianimprovementsto-14124P0.00NOTotals15002501750175000000PE1/1/20157/1/20156/1/2017STP(U>640160800800NWBradyRoadNW16thtoNW25thfrom:Widening,hikelanesPRWOTHEROTHER1000800200200800CCNSTP(U)1680720160040005003500Gto:16203P0.58CEYESTTotals0232015201960580111000801)35005007/1/20167/1/20176/1/2018PKOTHER400100500400100NWCamasMeadowsDriveNWPayneSt.toNW60thAvefrom.NewconstructionRW606060CNOTHER220060028002800to:00315P0.41YESCETotals026007603360400280000160PE7/1/20167/1/20176/1/2018OTHER1204016012040NWLarkspurStreetNWI.akeRdtoNW60thfrom:Widening,sidewalkWRW100100100CNOTHERS170640810810Pto:004P030.13CEYESTCGTotals0290780107012014081000ALL1/1/2018STP(IJ)1800158033803380NW3HtliAvenueNWParkertoGrassValleyParkfrom:Widening,hikelanesPCGto16503P0.45CKYESTTotals01800015803380000.3380ALL1/1/2018WSDOT250025002500SR-14WestCamasSloughBridgefrom:Widento4lanesNOTE:PEphasebegan1/2006to:12603P2.25NOTotals250025000002500000ReportDate:6/3/2014PageIof10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTC2015FROM:TO2020HearingDale.AmendDale:(5/2/2014AdoptionDaleResolutionNoProjectIdentificationAPin/ProjectNoC.ProjectTitleDRoadNameorNumberE.Begin&EndTerminiFProjectDescriptionProjcclCostsinThousandsofDollarsFederallyFundedProjectsOnlybt/>oOFundSourceInformationB.S1TPIDExpenditureSchedule(l.ocalAgency)8IsT3<552r3£"iPhaseStart(yyvv).i2£StateFundCodet-FederalFundCodeKnvir.TypeR/WRequiredI2£'3§toFederalFundsLocalFundsSlateFundsTotalFluidsc|—1st2nd3rd4Ihthru6lh•g5§'o'£a.GStructureIDu.346121415172578910131618192021ALL1/1/201518018030303090ADACompliancefrom:Cilywidc(Ongoing)to:14728P00NOTotals18000180303030900ALL1/1/2018290290290Nil'PacificRimlloulevardla)SKPayneRdfrom:Trafficsignalto:16824P00NOTotals290029000290000ALL1/1/2019STP(IJ)OTHER7120200002000068806000NEGoodwinRoad/28thStreetNWCamasMeadowsDr.toNF:232ndAve.from:Widento5laneswithhikelaneswestofIngleWidento3laneswithbikelaneseastofIngleto:CE17915P1.72YESTotals71206000200000020000068800ALL1/1/2016140014001400llyheeRoadRealignmentSE15thSt.toSE20lhSt.from:NewconstructionCswto171001P0.05YESGPTTotals001400140000140000505050CN1/1/2017NIVLeadbetterDrive,Ph.2NWLakeRd.toNWParkerSt.from:Wideningwithbikelanes,sidewalkNotes:PEphasebegan1/2007PCTto:17IIP280.83YESGWSTotals000505000050ALL1/1/2018500500500NIV23rdAvenueNwAstortoNWSierrafrom:Widening,sidewalkto:12YES0004P0.235000Totals00500005000ReportDate:6/3/2014Page2of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM:HearingDale.AmendDale:2015TO20206/2/2014AdoptionDaleResolutionNoProjectIdentificationAPin/ProjectNoC.ProjectTitleI)RoadNameorNumberC.Begin&EndTerminiK.ProjectDescriptionProjectCostsinThousandsol~DollarsFederallyFundedProjectsOnlyaaItB.STIPIDFundSourceInformationExpenditureSchedule(LocalAgency)uv</>1$agPn2>lPhaseStart§CL,2•5'is-FederalFundCodeStateFundCodeEnvirTypeR/WRequired3§C/33FederalFundsStaleFundsLocalFundsTotalFunds(yyyy)gf—1st2nd3rd4111thru6thD§'o'££G.StructureIDu.3245678910II121314151617181920216/1/2019ALL310031003100LakeRoadNWLacnmasLanetoNKEverettfrom:Widening,sidewalkto;161303P0.45ITSTotals3100310031000000006/1/2019PE400400400NewNUCAE/VVArterialNE14thSt.toEverettRdfrom;NewconstructionIncludesCriticalAreasandAlignmentInvestigationto:001415P2.00Totals040000400400000PE6/1/2019200200200NE9(hStreetNE232ndAvetoNE242ndAve.from:NewconstructionIncludesCriticalAreasandAlignmentInvestigationto:001515P0.50Totals000200200002000ALL6/1/2019260260260NWMarylandStreetNWI9lhtoNW24thfrom:NewconstructionCSwto191601P0.25NOGPTTotals260000260000260110110PE1/1/2017I/1/20186/1/2019110NIVAstorStrcel/NJV11thAvenueNW16lhAve.toMcIntoshRd.front:Widening,bikelanesIncludespathonForestHomeRoadfromForestHomeLanetoAstorStreetPI10noRW11017501750CCN1750Gto:1717030.62YESPT1Totals0197019700no1860000RW2202201/1/20206/1/2020220NWIMhAvenue,etaINWAstortoNW16lli,includeNWHoodfrom:Widencurb,sidewalkSCN194019401940WPto:161803P0.51YESICTotals021602160000216000ReportDate:6/3/2014Page3of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROMHearingDateAmendDale2015TO:20206/2/2014AdoptionDale:ResolutionNo:*ProjectIdentificationAPin/ProjectNoC.ProjectTitle1)RoadNameorNumberE.Begin&EndTerminiF.ProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnlyS3SIt-OBS'I'IPIDFundSourceInformationExpenditureSchedule(LocalAgency)uI85IsSio•2*zPhaseStart§O,£.*PFederalFundCodeStateFundCode££'Knvir.TypeR/WRequired3o•§FcilcralFundsStateFundsLocalFundsTotalFunds§tyyyy)1B2nd3rd1st4ththru6thH'1£(1StructureIDIn3I245678910II12131415161718192021PH1/1/2020555NW1SthAvenueNWWhitmanSt.toNWBradyRdfrom:NewconstructionwithbikelanesPOTto.161901P0.26CWsTotals55050(I0001/1/2020PK555NW18thAvenueNWWhitmanSt.toWestCityLimitsfrom:Widening,bikelanesWSPto:162003P0.40TCCi5Totals050500001/1/2020ALL211021102110NE43rdAvenueCsfrom:SR-500Widento3laneswithbikelanesto:EastCityLimitsG1721P030.36YKSPTTotals002110211000211000PE1/1/2020555NW43rd/NWAstor-NWSierratoNW3SthSPfrom:Widening,bikelanesCto002203P50GITotals550000005PE1/1/2020555NorthDwyerCreekMatterPlanStreet"B"NWFribcrgSl./StrunktoNWLarkspurSt.from:NewconstructionCSwto:002315P0.90OPTTotals005500050iReportDate:6/3/2014Page4of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROMHearingDaleAmendDale2015TO20206/2/2014AdoptionDaleResolutionNoProjectIdentificationAPin/ProjectNo.C.ProjectTitleI).RoadNameorNumberE.Begin&EndTerminiKProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnlyISu1FundSourceInformationBSTIPIDExpenditureSchedule(LocalAgency)IUt/>la"oi£aoz3l&PhaseStail(yyyy)cu3£t'FederalFundCodeStateFundCodeHnvirTypeR/WRequired38(/3FcdciniFundsr.SlateFundsLocalFundsTotalFundscI—1st2nd3rd4ththru6lhg5§'S'o.OStructureIDu-&.31416171819I245678910II12131520211/1/2020PH555NWPayneStreetNWLakeRd.toNWCamasMeadowsDrfrom:WideningCGPto0003P240.40T55005Totals00001/1/2020555PHNorthIhvyerCreekMasterPlanStreet"A"NWLakeRd.toNWCamasMeadowsDr.from:NewconstructionCswto:002515P0.64GPTTotals550500000PH1/1/2020555NWMcIntoshRoadNWBradyRdtoNW11thAve.from:Widening,bikelanesPGCto.002615P1.2T55Totals00000055870ALL1/1/202058705870NEWoodhurnDriveSE283rdAve.toSE15thSt.from:NewconstructionIncludes23rdStrealignmentCSwto:27YHS0001P70GPTTotals000587058700005870PE1/1/2020555SE15thStrcet/NourseRoadCsfrom:CamasHighSchoolto:NH283rdAve.Widento3laneswithbikelanesW072815P0.59GPTTotals50005000555PE1/1/20205NEmillStreetNE192ndAve.toNEGoodwinRd.from:Newconstruction(potentialalternatealignment)to:002915P0.67tTotals550050000ReportDate:6/3/2014Page5of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM:2015TO:2020HearingDale.AmendDate:6/2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNo.C.ProjectTitleD.RoadNameorNumberE.Degin<fcEndTerminiFProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnly1ocIt-OFundSourceInformationBSflPIDExpenditureSchedule(LocalAgency)uS!IS2'rl*lPhaseStart(yyyy)a.§I£&FederalFundCodeStateFundCodeKnvir.TypeR/WRequired38'3FederalFundsSlateFundsLoealFluidsTotalFundsgf51st2nd3rd4ththru6ths'o'££GStructureIDu.3I245678910121314151617181920211/1/2020PH555NE2KiltStreetNK232ndAvetoNK242ndAvefrom:Widento3laneswithbikelanesto:173015P0.50Totals0550050001/1/2020PH555NWCamasMeadowsDriveNH13thSttoNHIStliStfrom:Newconstruction(potentialalternatealignment)to.003115P0.20Totals5550000006/1/2020PH555NE232ndAvenueNH28thtoNH9thSt.from:Widento3laneswithbikelanesto:173215P0.97Totals005500500PE6/1/2020555NE242ndAvenueNE28thSt.toNE14thSi.from:Widento3laneswithbikelaneto:003315P0.70Totals000550050PE6/1/2020555.SR-300(EverettSt./Rd.)NWLakeRd.toSE4thSt.from:Widento3laneswithbikelaneto:163415P1.08Totals005500050PE6/1/2020555AIEIngleRondExtensionGoodwinto232ndAvefromNewconstructionto:003515P1.00Totals055000500ReportDate:6/3/2014Page6of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM2015TO:2020HearingDaleAmendDale6/2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNoC.ProjectTitleD.RoadNameorNumberE.Begin<fcEndTerminiK.ProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnlyuSIfCFundSourceInformationBSTIPIDExpenditureSchedule(LocalAgency)0StI®S<52nH:1zlig.PhaseStart2FederalFundCode2in-stateFundCodeHnvir.TypeR/WRequired|f3IrFederalFundsLocalFundsTotalFundsStateFunds(yyvv)|—3rd1st2nd4ththru6th5§'o'££(iStructureIDJ-3III24567891012131415161718192021I/1/2019ALL290290290NWBradyRoad(a)NW16thAvefrom:Trafficsignalto:14362400PNOTotals290000290029000ALL1/1/2019290290290NWLakeRoadUpNWSierraStfrom:Trafficsignalto:163700NO24PTotals2902900000002901/1/2020ALL290290290NEGoodwinRoad(aNil'CamasMeadowsDrivefrom:Trafficsignalto:380024P00NOTotals002902900000290PE1/1/2020555NIVPacificRim(a)ParkerStreetfrom:Trafficsignalto-163915P00Totals50005000555PE1/1/20205SR-S00(a)LcadbctterRoadfrom:AccessControlto:1640P1500Totals000550005PE6/1/2020555SR-500(a).NewE/iVArterialfrom:Trafficsignalto:164115P005Totals00500050ReportDate:6/3/2014Page7of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM:HearingDale.AmendDale:2015TO:20206/2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNo.C.ProjectTitleD.RoadNameorNumberE.Begin<fcEndTerminiK.ProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnly«53-§I-qFundSourceInformationB.STIPIDExpenditureSchedule(LocalAgency)iIsg211PhaseStail(yyyy).;2FederalFundCodeStateFundCodeHnvirTypeR/WRequired1£>acnFederalFundsStateFundsLocalFundsTotalFluidsc51st2nd3rd4ththru6lhJ§•o'I£OStructureIDLL,a.3I245678910121314151617181920216/1/2020555PHNE28thStreet(a]242ndAvenuefrom:Trafficsignalto.15P164200Totals5550000006/1/2020PH555NEGoodwinRoad'«>NHIngleRdfrom:Trafficsignalto.1715P4300Totals5505000006/1/2020PH555SR-500(a)NHLakeRdfrom:Roundaboutto:164415P00Totals550050000PE5556/1/2020SR-500-olNE14thAve.from:ControlledAccessto:164524P00Totals000550005PE6/1/2020555NE232ndAvenue(a)9thStreetfrom:Roundaboutto:004615P00Totals000550005PE6/1/2020555NE232ndAvenueIdIngleExtensionfrom:Roundaboutto:004715P00ITotals550050000iReportDate:6/3/2014Page8of10
Agency:CityofCamasCo.No.:06CityNo.:0145Co.Name:ClarkCo.MPO/RTPO:RTCFROM20ISTO:2020HearingDaleAmendDale(./2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNoC.ProjectTitleDRoadNameorNumberE.Begin<fcEndTerminiF.ProjectDescriptionProjectCostsinThousandsofDollarsFederallyFundedProjectsOnlye1>S-CFundSourceInfonnationBSTIPIDExpenditureSchedule(LocalAgency)OSii13"3S'2C3£Z|jt8.PhaseStart(yyyy)§2.5'FederalFundCodeKnvir.TypeR/WRequiredStateFundCode2§C/)'5FederalFundsStateFundsLocalFundsTotalFundscI—1st2nd3rd4ththru6th5§'S'£(iStructureIDUHa,3141516171820211245678910111213196/1/20154200CN42007007007002100PavementTreatments(maintenance&preservation)Pfrom:Overlays,surfacetreatmentsto:004847P00NO700Totals04200420070070021000012501250250ALL250750GReconstructsWfrom:Cilywidcto.004904P00NO12501250250250750Totals0000CN1/1/2016CDBG45050500100100300SidewalkProjectsfrom:SidewalkinstallationsCitywideto:005028P00NOIotaIs5001000450050010030015CN1/1/201675751545CurbRampProjectsfrom:Futurecurbrumpinstallationsto005128P00NOTotals00(I07575151545250CN1/1/2015STP(E)50250200NIVWhSharedPathSE201sttoBeechSt.from:to:165228P0.30NOTotals502502500020000050ALL1/1/2017200200150SharedPathImprovementsCilywidcfrom:to53NO0028P00Totals2002000050150000ReportDate:6/3/2014Page9of10
Agency:CityofCamasCo.No.:06CityNo.:0145,Co.Name:ClarkCo.MPO/RTPO:RTCFROMHouringDaleAmendDale2015TO:2020(i/2/2014AdoptionDale:ResolutionNo:ProjectIdentificationAPin/ProjectNo.C.ProjectTitleI)RoadNameorNumberE.Begin&EndTerminiFProjectDescriptionProjectCostsinThousandsol'DollarsFederallyFundedProjectsOnlyo(AO•5X>FundSourceInformationB.SIIPIDExpenditureSchedule(LocalAgency)u8gfi!“3aS'nn32PhaseStaid(yyvv)a,8FederalFundCodeStateFundCodeKnvir.TypeR/WRequireda-23r=FederalFundsStaleFundsLocalFluidsTotalFluidsg1st2nd3rd4ththru6th51§£O.StructureIDu-3I24567X910II121314151617181920211/1/2016ALL2502505050150SafelyProjectsfrom:FuturesafetyprojectsIncludestrafficrevisions.NWFargoCurve.SafetyAnalysisto.005421P00NOTotals25025005050150000I/1/2016CN202020StormUrateReplacements(HikeImprovements)from:Stormgratereplacementsforbikelaneimprovementsto:55PNO0038000Totals02020020000I/1/201625515CN255FutureHikeRouteImprovementsCityvvidefrom:Futurebikerouteimprovementsto.56PNO002800Totals2525551500001/1/2015CN12012020202020StreetLightingCilywidcfrom:StreetLightingto005721P00NOTotals001201202020202010001000ALL1/1/2020BR800200NE3rdAvenueWashuugalRiverBridgefrom:Seismicruling,scourcritical,andfoolingrehabilitationto:140258P00NOTotals0800020010000001000iReportDate:6/3/2014Page10of10
9.Appendices
A.Six Year Form Instructions
Heading
Agency
County No.
City No.
MPO/RTPO
Enter name of the sponsoring agency.
Enter the assigned number (see LAG Appendix 21.44).
Enter the assigned number (see LAG Appendix 21.45).
Enter the name of the associated MPO (if located within urbanized area)or
RTPO (if located in a rural area).
Enter the date of the public hearing.
Enter the date this program was adopted by council or commission.
Enter Legislative Authority resolution number (if applicable.)
Enter the date this program was amended by council or commission.
Hearing Date
Adoption Date
Resolution No.
Amendment Date
Column Number
1 .Functional Classification.Enter the appropriate 2-digit code denoting the Federal
Functional Classification.(Note:The Federal Functional Classification must be one
approved by FHWA.)
Description
00 -No Classification
Rural (<5000 pop.)
01 -Interstate
02 -Principal Arterials
06 -Minor Arterials
07 -Major Collector
08 -Minor Collector
09 -Local Access
Urban (>5000 pop.)
11 -Interstate
12 -Freeways &Expressways
14 -Other Principal Arterials
16 -Minor Arterial
17 -Collector
19 -Local Access
1.Priority Numbers.Enter local agency number identifying agency project priority
(optional).
2.Project Identification.Enter (a )Federal Aid Number if previously assigned;(b)
Bridge Number;(c)Project Title;(d )Street/Road Name or Number/Federal Route
Number;
(e)Beginning and Ending Termini (milepost or street names);and (f)Describe the Work
to be Completed.
4.Improvement Type Codes.Enter the appropriate federal code number.
SEE APPENDIX A
5 .Funding Status.Enter the funding status for the entire project or phase that
describes the current status .
S -Project is ‘selected’by the appropriate selection body and funding has been
secured by the lead agency.
P -Project is subject to selection by an agency other than the lead and is
listed for planning purposes.(Funding has not been determined .)
6.Total Length.Enter project length to the nearest hundredth (or code “00”if not
applicable).
7.Utility Code(s).Enter the appropriate code letter(s)for the utilities that need to
be relocated or are impacted by the construction project.
G -Gas
P -Power
S -Sewer (other than agency-owned )T -Telephone
W -Water
C -Cable TV
O -Other
8.Project Phase .Select the appropriate phase code of the project.
PE -Preliminary Engineering,including Design (or Planning)
RW -Right of Way or land acquisition
CN -Construction only (or transit planning or equipment purchase)
ALL -All Phases:from Preliminary Engineering through Construction
9.Phase Start Date.Enter the month/day/year in MM/DD /YY format that the
selected phase of the project is actually expected to start.
10 .Federal Fund Code.Enter the Federal Fund code from the table.
SEE APPENDIX C
11.Federal Funds.Enter the total federal cost (in thousands)of the phase
regardless of when the funds will be spent.
12 .State Fund Code .Enter the appropriate code for any of the listed state funds
to be used on this project.
SEE APPENDIX C
13 .State Funds.Enter all funds from the State Agencies (in thousands )of the phase
regardless of when the funds will be spent.
14.Local Funds.Enter all the funds from Local Agencies (in thousands )of the phase
regardless of when the funds will be spent.
15.Total Funds.Enter the sum of columns 10,12,and 14 .(Auto-calculation in the
“STIP Too”program.)
16-19.Expenditure Schedule -(1st,2nd,3rd,4th thru 6th years).Enter the
estimated expenditures (in thousands)of dollars by year.(For Local Agency use.)
20.Environmental Data Type.Enter the type of environmental assessment that will be
required for this project.(This is “required”for Federally funded projects ,but may be
filled in for state or locally funded projects .)
EIS -Environmental Impact Statement
EA -Environmental Assessment
CE -Categorical Exclusion
21.R/W Certification.Click Y if Right of Way acquisition is or will be required.If yes ,
enter R /W
Certification Date,if known.(This is “required”for Federally funded projects
APPENDIX A
IMPROVEMENT TYPE CODES
01 New Construction Roadway
Reconstruction,Added Capacity
Reconstruction,No Added Capacity
4R Maintenance Resurfacing
4R Maintenance -Restoration &Rehabilitation
4R Maintenance -Relocation
Bridge,New Construction
Bridge Replacement,Added Capacity
Bridge Replacement,No Added Capacity
Bridge Rehabilitation,Added Capacity
Bridge Rehabilitation,No Added Capacity
Preliminary Engineering
Right of Way
Construction Engineering
Planning
Research
Environmental Only
Safety
Rail/Highway Crossing
Transit
Traffic Management/Engineering -HOV
Vehicle Weight Enforcement Program
Ferry Boats
Administration
Facilities for Pedestrians and Bicycles
Acquisition of Scenic Easements and Scenic or Historic Sites
Scenic or Historic Highway Programs
Landscaping and Other Scenic Beautification
Historic Preservation
Rehab &Operation of Historic Transp.Buildings,Structures,Facilities
Preservation of Abandoned Railway Corridors
Control and Removal of Outdoor Advertising
Archaeological Planning &Research
Mitigation of Water Pollution due to Highway Runoff
Safety and Education for Pedestrians/Bicyclists
Establishment of Transportation Museums
Special Bridge
Youth Conservation Service
Training
Utilities
Other
Debt Service
Systematic Preventive Maintenance
03
04
05
06
07
08
10
11
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
47
APPENDIX C
FEDERAL FUND CODES
5307 FTA Urbanized Area Formula Program
FTA Bus and Bus Facilities
FTA Fixed Guideway Modernization
FTA New Starts
FTA Elderly Persons and Persons with Disabilities
FTA Rural Area Formula Grants
FTA Job Access &Reverse Commute Program (JARC)
FTA New Freedom Program
Discretionary Programs such as Alternatives Analysis (5339)and
TIGGER Program
Bureau of Indian Affairs
Bridge Replacement/Rehabilitation Program
Coordinated Border Infrastructure
Community Development Block Grant (Dept,of Commerce)
Congestion Mitigation and Air Quality
Demonstration Projects (High Priority,Sect.112,115,117,125 and 129 )
Ferry Boat Discretionary
Interstate Maintenance Discretionary
Intelligent Transportation Systems
Public Lands Highways (Federal Lands)
Scenic Byways
Surface Transportation Priorities
Transportation,Community &System Preservation Program
Department of Defense
Freight Mobility Strategic Investment Board
Interstate Maintenance
Indian Reservation Roads
National Highway System
Safe Routes to Schools
Surface Transportation Program (WSDOT Use Only)
Surface Trans.Program -Enhancements
Surface Trans .Program -Legislative Earmarks
Surface Trans.Program-Safety (Includes Highway)Safety Improvement
Program,Hazard Elimination,Railway/Highway Crossing Program and 2010-
15 County Road Safety Program)
Surface Trans.Program -Rural Regionally Selected
Surface Trans.Program -Urban Regionally Selected
5309(Bus)
5309 (FG)
5309(NS)
5310
5311
5316
5317
FTA Discretionary
BIA
BR
CBI
CDBG
CMAQ
DEMO
Discretionary-FBD
Discretionary-IMD
Discretionary-ITS
Discretionary-PLH
Discretionary-SB
Discretionary-STP
Discretionary-TCSP
DOD
FMSIB
IM
IRR
NHS
SRTS
STP
STP(E)
STP(L)
STP(S )
STP(R)
STP(U)
STATE FUND CODES
CRAB
FMSIB
PWTF
SRTS
County Road Administration Board
Freight Mobility Strategic Investment Board
Public Works Trust Fund
Safe Routes to Schools
Transportation Improvement Board
Transportation Partnerships Program
WSDOT funds
Any other state funds not listed
TIB
TPP
WSDOT
OTHER