CON0000240 - 6/6/2016 - North Shore STS Cost Share with CSD (Clerks Office Use Only,
CONTRACTS & AGREEMENTS Record No.
cia Required Information Date 1/28/2019
WASHINGTON Cover Sheet ® NEW
❑ REPLACEMENT
The original paper copy of ALL Camas contracts/agreements/amendments are to be retained in the City's centralized filing system,
managed by the City Clerk's Office.
• RES No. 16-009, contract and agreement thresholds-authorizes Mayor/designee to enter into/execute the following contracts/
agreements without individual approval of each contract/agreement by City Council:
o Professional Service Contracts/Agreements-including, but not limited to contracts/agreements for architectural,
engineering, legal, and consulting services involving a cost or fee of less than$50,000.
o Maintenance/Service Contracts-for nonprofessional services involving a cost or fee of less than$50,000.
o Lease Agreements-for materials, supplies,and equipment where expenditures or fee do not exceed $50,000 per year.
o Public Works Projects-Small Works Roster Projects with a single trade involving expenditures of less than$100,000 and
Small Works Roster Projects with multiple trades involving expenditures of less than$150,000.
o Public Works Projects-Capital Maior Maintenance Projects in excess of limits set forth above will proceed to Council for
approval.
o Change Orders—Mayor/designee has the authority to execute Change Orders up to 10%of contract total, provided they are
within limits of original contract and consistent with scope and intent of authorized project.
*** FILL OUT ALL APPLICABLE FIELDS AND ENSURE REFERENCED EXHIBITS ARE ATTACHED *"*
City Staff Contact(Responsible) Staff Contact Phone# Staff Contact Title
Sam Adams ext.4203 Utilities Manager
Contracting AgencykParty Contracting Agency Contact Contact Phone or Email
Camas School District Administration 360.335.3000
City Department/Division Dept.Admin Assistant Additional Contact Information
Public Works Ronda S verson ext.4256
Type of ❑Construction/Small Works Project No Additional Contract Information(key words,other agency-related,
Contract WS-681 C ordinance,amendment no.to original contract dated)
❑Consultant/Professional Services North Shore Sewer Transmission System
El Contract for Services
❑G rant
®Interlocal Agreement(ILA) Recording Number& If Council Approval Required(see limits above),provide date of
❑Franchise Agreement Date Council approval: 6/6/2016 RES No.
❑Development Agreement
❑Amendment/Supplement to Budget Funded Account#
Contract No. OR
❑Other(explain) Other Funding Source:
Contract Start Date Expiration Date Contract/Project Terms,af Renewai or Termination&Extensions
6/6/2016 Project Accepted as complete Completion Date (Rg-dUIRED)No termination date
2/4/2019 2/4/2019
Original or Copy Media Type Specific Location of Record
® Original ❑ Copy ® Paper ❑ Electronic ❑ CD-DVD ❑ Network Location
❑ Eng. Copy ❑ Video/Audio Tape ❑ Flash Drive ❑ Building Cabinet Number
If copy,where is original? ❑ Other ❑ Additional Copy Locations
FOR ADMINISTRATIVE ASSISTANT USE ONLY
Disposition Authority#(DAN)(REQUIRED) Records Series Title Retention/Dispo- Event Cut-off&Date
GS50-01-11 Rev.4 1.5 Contracts/Agreements sition Action following final payment to
6 years Cit
Designation/Remarks Comments
Essential ❑Archival-Appraisal Req'd ❑ Archival-Permanent
® Non-Archival, Destroy After Retention Met ❑ Confidential
❑ Other
Routing Signatures/Initials: EXEMPT INFORMATION(statute and page Nos):
➢ City Attorney
CI ick or tap here to enter test.
➢ City Administrator
➢ Department Manager/Director
➢ Finance Director
➢ City Engineer(s)
➢ Other
FldJ?D rf7PV F11 F rMnR/'nnF — RFn• Pormnnonf VFllnW Fcv..dnl R►l/F• Fvanf_Rncod CRFFN• Fr ;ra inn nnfo
ORIGINAL
INTERLOCAL AGREEMENT
AGREEMENT made this day by and between the CITY OF CAMAS, a municipal
corporation organized under the laws of the State of Washington,hereinafter referred to as
"City", and CAMAS SCHOOL DISTRICT NO. 117, a political subdivision organized under the
laws of the State of Washington,hereinafter referred to as "School District".
RECITALS:
WHEREAS, RCW Chapter 39.34, the Interlocal Cooperation Action, provides that units
of local government may enter into agreements for the performance of any and all functions and
activities that a party to the Agreement, its officers, or agents have authority to perform; and
WHEREAS, the City intends to construct sewer system improvements identified in the
City's Capital Facilities Plan across an area identified as the North Shore(previously known as
the North Urban Growth Area), known as the North Shore Sewer Transmission System (NS-
STS) Improvements; and
WHEREAS,the City has issued water and sewer revenue bonds to finance design and
construction of the NS-STS improvements; and
WHEREAS, the School District has acquired certain real property situated within the
North Shore to be developed into a school site which adjoins the NS-STS Improvements; and
WHEREAS, the School District will be required to design and construct certain water
system improvements to serve the school site in accordance with the City's Water System Plan
and development standards; and
WHEREAS,the City and School District recognize that financial contributions and other
Interlocal Agreement Page 2
Y
collaborative efforts would be in the best interest of the City and the School District to provide
the improvements as described herein; and
WHEREAS, the parties desire to enter into an agreement to delineate their respective
obligations for the joint future development of the NS-STS improvements and Water System
Improvements to serve the school site (jointly called "The Project") as described herein.
NOW, THEREFORE, in consideration of the terms, conditions, covenants and
performance contained herein, the parties named below agree as follows:
Section 1. PARTIES: The City and the School District, each constituting the public
agency as defined by RCW Chapter 39.34, are parties to this Agreement and mutually promise to
the terms and conditions described herein.
Section 2. PURPOSE: The purpose of this Agreement is to establish a process by
which the School District will financially contribute towards The Project, specifically for the
design, permitting, and construction costs associated with completion of the Water System
Improvements to serve the school site, and to outline the respective responsibilities of each party
for The Project completion and timing.
Section 3. LEAD AGENCY DESIGNATION: No new or separate legal or
administrative entity is created by this Agreement. For the purposes of the administration of
funds received, the City,by and through the Camas City Finance Director, will act as the lead
agency regarding management of design,permitting and construction, and will receive and
disburse all funds otherwise associated with the Project as defined herein. The City will provide
the School District every opportunity to participate in all discussions,meetings and design and
Interlocal Agreement Page 3
construction decisions related to the water system improvements portion of the project.
Administration of any bond proceeds shall be conducted as outlined in the respective bond
contracts.
Section 4. CONSTRUCTION: The anticipated schedule for completion of The Project
includes completing design in the first quarter of 2017 and completing construction in summer
2018. The City will use its best efforts to meet the anticipated schedule. The School District
understands and agrees the City cannot guarantee meeting the anticipated schedule due in part to
unknown permitting requirements and the potential for unanticipated construction delays. The
City and the School District will work in good faith to expedite The Project, provide adequate
notice to the other party of any anticipated delay factors, and work through any unforeseen delays
in an expedited manner. This Agreement is solely for the benefit of the parties and does not
confer rights to any other individual or person. Neither party shall hold the other liable for delays
to the Project which may impact individual commitments to others not subject to this Interlocal
Agreement.
Section 5. FINANCING: The respective costs and cost share of the Project shall be as
outlined in Exhibit"A", attached hereto and by this reference incorporated herein, which
includes estimated costs for Pre-Design, Final Design and Permitting, Construction and
Construction Management Services. The City, acting as the Lead Agency, shall administer the
contracts to complete The Project and be responsible for processing and paying all invoices and
fees for services rendered by consultants, contractors and other agencies. Once payments are
made by the City, the City will submit invoices to the School District, who shall have 15 days to
Interlocal Agreement Page 4
submit payment to the City. If payment is not received within 30 days, the City's standard late
charges and fees may be applied at the discretion of the City.
Section 6. UTILITY TAXES. The parties recognize that the Project is being developed
to provide water supply to the parties. Nothing contained within this Agreement shall relieve any
party from utility taxes which may otherwise be owed.
Section 7. TERMINATION: This agreement shall terminate upon the occurrence of
any of the following, whichever is sooner: (1) Upon completion of the Project; or(2) Upon 180
days' advance written notice of any party to this Agreement, on the following conditions relating
to any voluntary termination: Prior to any such termination, the City and School District, through
their respective representatives, will propose for approval by the governing bodies of each party a
plan to wind up the Project affairs, and provide for a final allocation of invoices and fees as set
forth in Section 5 herein.
Section 8. INSPECTION OF RECORDS: Any duly authorized representative of the
parties shall have the right to inspect the records related to the Project as defined in the Purpose
section of this Agreement upon ten days prior written notice.
Section 9. MODIFICATION: This Agreement may only be modified or amended by
written amendment and modification approved by each of the parties to this Agreement.
Section 10. INDEMNIFICATION: To the maximum extent permitted by law, Camas
and the School District indemnify and hold harmless the other party and all of its officers,
officials, employees, and volunteers from any and all claims, demands, injuries, losses, suits,
actions, fines, penalties, and liability of any kind, including attorney fees, to the extent they arise
Interlocal Agreement Page 5
out of or are related to the performance of this Agreement by the indemnifying party or its
officers, officials, employees, volunteers, agents, representatives, consultants, contractors, or
subcontractors. This indemnity is not limited by a limitation on amount or type of damages,
compensation, or benefits payable by or for the indemnifying party under workers' compensation
acts, disability benefit acts, or other employee benefit acts. This indemnity is specifically and
expressly intended to constitute a waiver of the indemnifying party's immunity under
Washington Industrial Insurance (Title 51 RCW) with respect to only the other party, and only to
the extent allowable by law and necessary to provide the indemnified party with a full and
complete indemnity of claims made by the indemnifying party's employees. This waiver has
been mutually negotiated. The provisions of this Subsection survive the expiration or
termination of this Agreement.
Section 11. FORCE MAJEURE. If a party is rendered unable by Force Majeure, to
carry out, in whole or part, its obligations under this Agreement and such party gives notice and
full details of the event to the other party as soon as practicable after such occurrence, the
obligations of the party affected by the event (other than the obligation to make payments due for
performance prior to the event) shall be suspended to the extent required. Under this Agreement,
"force majeure" shall mean acts of God, wars, strikes, lockouts, labor disputes, civil disorder,
acts of terrorism, fires, floods, volcanic eruptions, earthquakes or other causes beyond the
reasonable control of the affected party.
Section 12. EFFECTIVE DATE: This Agreement shall become effective and
commence upon the execution of the Agreement by all parties named below.
Interlocal Agreement Page 6
Section 13. DISPUTE RESOLUTION:
13.1 Negotiations. The parties agree to make all reasonable efforts to resolve through
informal, good faith negotiations any disputes concerning the terms and conditions or
performance of this Agreement. In the event of a dispute, including a claimed breach of this
Agreement, notice of the dispute shall be provided in writing and shall be delivered in the
manner set forth in Section 16. The notice shall set forth with reasonable specificity the factual
basis for the claimed dispute. Both parties shall jointly cooperate to informally resolve any
disputes as quickly and efficiently as possible,but in any event not more than sixty(60) days
from the date of the notice unless extended by mutual agreement of the parties.
13.2 Voluntary Mediation. If a dispute cannot be resolved through direct discussions,
mediation may, by mutual consent,be initiated. In the event the parties determine to initiate
mediation, a mutually acceptable mediator shall be selected by the parties for the purpose of
facilitating the mediation process. The mediator shall be selected based on his or her expertise
with the nature of the matter in dispute and their ability to facilitate a settlement. The parties
agree to provide all documentation and information requested by the mediator and in all other
regards to cooperate fully with the mediator. The costs of mediation shall be shared equally
between the parties.
13.3 Arbitration. In the event the dispute is not resolved in mediation, the dispute shall
be resolved by arbitration pursuant to the Clark County Local Rules for mandatory arbitration,
PROVIDED, the Local Rules regarding jurisdiction limits shall not apply, or by other means
provided the parties to the dispute agree. In the event of a dispute, the prevailing party would be
Interlocal Agreement Page 7
entitled to receive attorney's fees.
Section 14. PRIOR AGREEMENTS: This document contains the entire agreement
between the parties. There are no promises, terms, conditions, or obligations other than those
contained herein. This contract shall supersede all previous communications, representations, or
agreements, either verbal or written,between the parties.
Section 15. INSURANCE: Each party shall obtain and keep in full force and effect
liability insurance protecting itself and its employees, officers and agents, and the party, its
employees, officers and agents, for claims of any persons for injuries to life, person or property
by reason of anything done or permitted to be done or suffered or admitted to be done by the
parties in the administration of the project. If the City withdraws from the Washington Cities
Insurance Authority, the City shall deliver a certificate of insurance showing compliance with
this section.
Section 16. NOTICES: All notices required by this Agreement must be in writing by
hand delivery or certified mail,return receipt requested.
If to the City, notice must be sent to:
City Administrator
City of Camas
616 NE 4b Avenue
Camas, WA 98607
Interlocal Agreement Page 8
If to the School District, notice must be sent to:
Superintendent
Camas School District
841 NE 22nd Avenue
Camas,WA 98607
Notice is considered given upon delivery or, if mailed,upon the earlier of actual receipt
or three(3)business days after the date of mailing.
Section 17. SEVERABILITY: All provisions of this Agreement are to be interpreted
independently. If a provision is determined illegal,void and/or unenforceable by a court of law
having jurisdiction in this matter, all other provisions of this Agreement remain in full force and
effect and shall be binding upon the parties.
Section 18. COUNTERPARTS: For the convenience of the parties,this Agreement
may be executed in counterparts.
Section 19. GOVERNING LAW: This Agreement shall be governed and interpreted
under the laws of the State of Washington.
Section 20. FILING: This Interlocal Agreement shall be filed and recorded with the
Clark County Auditor and the parties to this Agreement shall post the Agreement on their official
website in accordance with RCW 39.34.040.
DATED this day of f I -�, , 2016.
CITY OF A
By: L <1
Mayor
Interlocal Agreement Page 9
Attest: V�
Clerk
S SCHO ISTRICT NO. 117
By:
Superintendent
Technical Memorandum - Appendix A
To: Sam Adams,Steve Wall-City of Camas
From: Tim Kraft
700 IY/arbington Street
S,dte 401 Prepared By: Tim Kraft
Vancouver, ISA 98660
Phone(360)737-9613 Date: May 10'h,2016
Fax(360)737-9651
Subject: North Shore-STS: Cost sharing with Camas School
District
Project No.: 17628
The Camas School District(District) intends to build a new school near the intersection of NE 9"'
Street and NE 232nd Avenue.In order to serve this new school with water and telecommunication
services,the District will install a new 12-inch waterline and fiber optic line in NE Leadbetter Road.
To combine efforts and resources,these will be designed and constructed with the North Shore
Sewer Transmission System and the District will enter into an agreement with the City of Camas to
participate in cost-sharing for design and construction of the waterline and fiber optic line.
This document describes the process for estimating cost-sharing of the preliminary design,final
design,and construction management tasks for the North Shore STS project.A summary of the
costs splits is shown in Table 1.
Table 1: Cost$haring Summary
Total Fee City Portion District Portion
Preliminary Design $1,089,774 $1,004,668 $85,106
Final Design $1,472,783 $1,333,873 $138,910
Construction
Management/Staking/DSC $1,625,598 $1,351,280 $274,318
Total $4,188,155 $3,689,821 $498,334
Preliminary design and final design contract values were used to determine cost sharing for those
tasks.As a scope and fee has not yet been prepared for construction management, staking and
design services during construction (DSC),these fees were estimated as 12 percent of the estimated
construction cost.This was used for the cost sharing for that task.
V:\PROJEM17600\17628\ProjectDocs\Reports\CSD-Cost Sharing\17628 CSD Cost Sharing Memorandum Combined V2 doc
i
North Shore STS:Camas School District Cost Sharing Page 2
i
j
Cost Sharing Methodology
The District's waterline is approximately 9,907 feet in length,and the city's sewer line is 24,675 feet
long.Approximately 39 percent of the sewer pipeline will be installed in the same corridor as the
District waterline,and approximately 325 feet of the waterline will not be parallel to the sewer line
but will receive the same services with this phase of the work.Thus,the total length of waterline is
40 percent of the length of the sewer line.Therefore,the proposed method for cost-sharing between
the city and district for design costs is to evenly split 40 percent of the design costs for tasks
applicable to both the sewer pipeline and the water pipeline. 1
s
Preliminary Design
The major tasks from the MUGA-STS preliminary design contract are shown below and those being
applied to both projects for cost sharing calculations are noted as such.
Task 1: Flow Projections
This task does not apply to the cost sharing agreement.
Task 2: Alternatives Evaluation
This task does not apply to the cost sharing agreement.
j
i
Task 3: Preliminary Design
This task does not apply to the cost sharing agreement.
l
3
Task 4: Survey and Mapping j
This task is included in the cost sharing calculations for the agreement.
Task 5: Geotechnical Investigation I
This task is included in the cost sharingcalculations for the agreement.
}
}
t
Task 6: Environmental Services [
This task is included in the cost sharing calculations for the agreement,except for Subtask 6.1 and
Subtask 6.9,which don't apply to the waterline.Note that Subtasks 6.4 through 6.8 were not used
on this project. '
Task 7: Cultural and Historic Resource Assessments
i
This task is included in the cost sharing calculations for the agreement.
Task 8: Right-of-Way Services
This task does not apply to the cost sharing agreement.
I
i
V:\PROJEC'1'\17600\17628\ProjectDocs\Reports\CSD-Cost Shamig\17628 CSD Cost Sharing Memorandum Combined V2doc
North Shore STS:Camas School District Cost Sharing Page 3
Task 9: Project Management
Subtask 9.1,Project Management is included in the cost sharing calculations for the agreement,but
Subtask 9.2,Project Meetings is not.Most meetings for this project were held before the waterline
design was part of the work,and the waterline was not discussed at the project meetings.
Task 10: Risk Management
This task does not apply to the cost sharing agreement.
Subconsultant Administration was proportioned for all tasks where subconsultants worked on the
tasks included in the cost sharing.
Expenses were allocated where used on the tasks included in the cost sharing.
Table 2 summarizes the costs for each of the tasks associated with both the city sewer system and
the District waterline project using the cost-sharing system described above.
Table 2: Cost Sharing Breakdown-Preliminary Design
Total Budget Camas School
Task Description b Task City of Camas District
1 Flow Projections $ 15,790 $ 15,790
2 Alternatives Evaluation $227,640 $227,640
3 Preliminary Des' $401,208 $401,208
4 Survey and Ma $ 95,450 $ 76,360 $ 19,090
5 Geotechnical Investigation
5.1 Geotechnical Data Review $ 820 $ 656 $ 164
5.2 Geotechnical Reconnaissance $ 14,760 $ 11,808 $ 2,952
5.3 Geotechnical Report $ 15,788 $ 12,630 $ 3,158
6 Environmental Services
6.1 Stream and Wetland Field Review and Report $ 7,892 $ 7,892
6.2 DARPA and CWA Compliance $ 996 $ 797 $ 199
6.3 WDNR Aquatic Use Authorization $ 1 ,670 $ 1,336 $ 334
Camas Critical Areas and Significant Tree
6.9 Permit $ 2,998 $ 2,998
7 1 Cultural and Historic Resource
V:\PROJEM17600\17628\ProjectDocs\Reports\CSD-Cost Sharing\17628 CSD Cost ShanngMemormdum Combined V2.doc
s
North Shore STS.•Camas School District Cost Sharing Page 4
Table 2: Cost Sharing Breakdown-Preliminary Design
Total Budget Camas School
Task Description by Task City of Camas District
i
Assessments
7.1 Background Review $ 5,852 $ 4,682 $ 1,170
7.2 Site Reconnaissance $ 6,138 $ 4,910 $ 1,228 '
73 Resource Surveys $ 54,446 $ 43,557 $ 10,889
7.4 Report $ 42,359 $ 33,887 $ 8,472
8 ht of Wa $ 2,000 $ 2,000
1
j
9 Project Management
9.1 Project Management and QA/QC $ 39,854 $ 31,883 $ 7,971
9.2 Project Meetings $ 49,782 $ 49,782
10 Risk Re ' ter $ 12,495 $ 12,495
i
Subconsultant Administration $ 29,900 $ 17,691 $ 12,209
Expenses $ 61,936 1 $ 44,666 $ 17,270
Project Total $1,089,774 $1,004,668 $85,106
3
s
j
s
i
i
j
j
j
4
3
I
V.\PROJECT\17600\17628\ProjectDocs\Reports\CSD-Cost Sharing\17628 CSD Cost Shanug Memorandum Combined V2.doc
North Shore STS:Camas School District Cost Sharing Page 5
Final Design
The major tasks from the North Shore-STS final design contract are shown below and those being
applied to both projects for cost sharing calculations are noted as such.
Task I: Survey and Mapping
This task is included in the cost sharing calculations for the agreement,except for Subtask 1.3,
Easements.
Task 2: Environmental Services
This task is included in the cost sharing calculations for the agreement except for Subtask 2.1,
Stream and Wetland Field Review and Report,and Subtask 2.8,Critical Areas and Significant Tree
permit.
Task 3: Geotechnical Investigation
This task is not included in the cost sharing calculations for the agreement.The scope for this task is
for contingency only.
Task 4: Cultural and Historic Resource Assessments
This task is included in the cost sharing calculations for the agreement,except for Subtask 4.2,which
is for additional archeological work within Camp Currie.
Task 5: Public Involvement
This task is not included ui the cost sharing calculations for the agreement.
Task 6: Real Property Services
This task is not included in the cost sharing calculations for the agreement.
Task 7: Land Use Permitting
This task is included in the cost sharing calculations for the agreement,except for Subtask 7.2,Site
Plan Review Application;Subtask 7.3,Building Permit Application;and Subtask 7.4,Clean Air
Permit.
Task 8: 60 Percent Design Phase
This task is included in the cost sharing calculations for the agreement for the utility coordination,
potholing,and pipeline design tasks only. Pump Station Design and Design Workshop costs are not
included.
Task 9: Contract Documents
This task is included in the cost sharing calculations for the agreement,using the pipeline costs only.
V:\PRODECT\17600\17628\ProjectDocs\Reports\CSD-Cost Sharing\17628 CSD Cost Sb Memorandum Combined V2.doc
. f
• - i
North Shore STS:Camas School District Cost Sharing Page 6
i
Pump station design costs are shown in the total column and in the City's column in Table 3,but
were not included in the cost share,and are not in the District's column.
1
Task 10: Project Management
This task is included in the cost sharing calculations for the agreement.
i
Task 11: Camas North Shore School Design Support(100 percent to Camas School District)
This task is fully allocated to the Camas School District,as it is for water system modeling to
support the waterline design.
i
Subconsultant Administration was proportioned for all tasks where subconsultants worked on the
tasks included in the cost sharing.
Expenses were allocated where used on the tasks included in the cost sharing.
Table 3 summarizes the costs for each of the tasks associated with both the city sewer system and r
the District waterline project using the cost-sharing system described above.
Table 3: Cost Sharing Breakdown-Final Design.
Total Budget by Camas School
Task Description Task City of Camas District
1
1 Survey and Mapping
E
1
1.1 Too hic Surve $ 27,240 $ 21,792 $ 5,448
1.2 RWat of Way and Boundary Survey $ 37,080 $ 29,664 $ 7,416
1.3 Easement Preparation $ 10,910 $ 10,910 {
2 Environmental Services
2.1 Stream and Wetland Field Review and Report $ 2,322 $ 2,322
2.2 TARPA and CWA Compliance $ 4,504 $ 3,603 $ 901
2.3 WDFW HPA Approval $ 876 $ 701 $ 175
E
2.4 ESA Compliance $ 956 $ 765 $ 191
2.5 Sole Source Aquifer Program Compliance $ 871 $ 697 $ 174 x
2.6 SEPA Compliance $ 2,258 $ 1,806 $ 452
2.7 Shoreline Master Program Permit $ 8,954 $ 7,163 $ 1,791
2.8 Critical Areas and Significant Tree permit $ 3,940 $ 3,940
3 Geotechnical Investigation $ 15,800 $ 15,800
s
V:\PROJEC'1'\17600\17628\PcojectDocs\Reports\CSD-Cost Sharing\17628 CSD Cost Sharing Memorandum Combined V2doc
North Shore STS:Camas School District Cost Sharing Page 7
Table 3: Cost Sharing Breakdown-Final Design
Total Budget by Camas School
Task Description Task City of Camas District
4 Cultural and Historic Resource Assessments
Archaeological shovel tests to be excavated within
4.1 Leadbetter Road $ 23,130 $ 18,504 $ 4,626
4.2 Archeolo gcal testina,and evaluation $ 158,133 $ 158,133
4.3 Inadvertent Discovery Plan(IDP) $ 2,995 $ 2,396 $ 599
5 Public Involvement $ 6,464 $ 6,464
6 Real Property Services $ 7,500 $ 7,500
7 Land Use Permitting
7.1 Pre-application Conference $ 1,352 $ 1,082 $ 270
7.2 Site Plan Review Application $ 2,376 $ 2,376
7.3 Building Permit Applications $ 2,376 $ 2,376
7.4 Clean Air Permit $ 2,376 $ 2,376
7.5 Utility Permits $ 1,312 $ 1,050 $ 262
7.6 NPDES/SWPPP $ 4,288 $ 3,430 $ 858
8 60 Percent Design
8.1 Utility Coordination $ 1,160 $ 928 $ 232
8.2 Potholing $ 2,016 $ 1,613 $ 403
8.3 Pipeline $ 87,600 $ 70,080 $ 17,520
8.4 Pump Stations $ 238,224 $ 238,224
8.5 Design Work-shop $ 12,326 $ 12,326
9 Contract Documents
9.1 Ninety Percent Des' $ 298,975 $ 272,010 $ 26,965
9.2 Final(Bid Ready)Documents $ 173,137 $ 156,008 $ 17,129
9.3 Bid Support $ 77,422 $ 73,777 $ 3,645
10 Project Management
10.1 Project Mans went and QA/QC $ 72,101 $ 57,681 $ 14,420
10.2 Project Meetings $ 34,919 $ 27,935 $ 6,984
11 Camas North Shore School Design Support $ 2,644 $ 2,644
11.1 Confirm Emsting System Capacity $ 9,378 $ 9,378
V:\PROJECT\17600\17628\ProjectDocs\Report5\CSD-Cost Shanng\17628 CSD Cost SL=l Memorandum Combined V2doc
. F
3
i
i
North Shore STS.•Camas School District Cost Sharing Page 8
:
Table 3: Cost Sharing Breakdown-Final Design
Total Budget by Camas School
Task Description Task City of Camas District
11.2 Modeling Analysis $ 6,636 $ 6,636
l
11.3 Modeling Documentation
Subconsultant Administration $ 44,844 $ 43,797 $ 1,047
Expenses $ 83,388 $ 74,644 $ 8,744
a
Project Total $1,472,783 $1,333,873 $ 138,910
Construction Management/Construction Staking/Design Services During
Construction
i
This task has not been scoped yet,but a budget value has been estimated as 12 percent of the total =
construction costs. This percentage was used to set a budget value for the cost sharing between the
two agencies and is shown in Table 4.
Table 4:Cost Sharing Breakdown—CM/CS/DSC
Camas School
Total Budget City of Camas District
Construction Management/Staking/DSC $1,625,598 $1,351,280 $274,318
l
l
l
Y
t
3
a
4
1
L
V:\PROJECT\17600\17628\PtojectDocs\Reports\CSD-Cost Shaw\17628 CSD Cost Sharing Memorandum Combined VZdoc
i